Experience

Telemetry

ACWWA
MTU programming architecture

RTU & control system support (collections & distribution)

Himalaya Vault Telemetry Integration

Elkhorn Booster Pump Station Telemetry updates and well integration

Telemetry network optimization

Engineering

Consolidated Mutual Water
Design/Build of Pump Station Control Systems, Telemetry Architecture, and HMI Screens.

Design/Build of new Maplegrove WTP SCADA Server Architecture, Database Architecture, and HMI Screens.

Design/Build of new Dewatering Building SCADA System instrumentation, Fiber Network, HMI Screens, and Database Architecture.

ACWWA
Design/Build of control systems, and SCADA integration of new water well and chlorination vault.

3rd party design review (well install)
control system and telemetry upgrades (pump station)

Aurora
Radio network improvements and reporting set up (Sonde)

EcoVapor
Control system design (oxygen destruction)

EcoVapor
Telemetry system management (cell radios at RTU's)

System Integration

Left Hand Water District
Spurgeon Water Treatment Plant Upgrades (6 MGD)

Left Hand Water District
Booster Station PLC Replacements (Siemans to Allen Bradley)

Arapaho Water & Wastewater Authority
Lone Tree Water Reuse Facility upgrades (2.4 MGD)

Evergreen
Evergreen Metro District Wastewater Plant Upgrades (0.5 MGD)

Kinross Gold Mine
Industrial Wastewater Plant Upgrades (100 GPM)

Kinross
Biotreatment Plant Upgrades

City of Thornton
New Transfer Pump Station (1 MGD)

ACWWA
Himalaya Vault Telemetry and SCADA Upgrades (1 MGD)

Elkhorn Vault Telemetry and SCADA Upgrades (300 GPM)

Kinross Gold Mine
Telemetry Systems (30 monitoring sites)

Waste Management
Landfill Flare Gas Monitoring (30+ flare monitoring units across the US)

EcoVapor
Vapor Recovery Systems (20 systems in DJ Basin)